Progress of the new soboba casino

broken image

This has allowed the zipper work to be completed on that side of the hotel.Īt level one, exterior glazing is nearing 100 percent completion. Something that may have been noticed by regular travelers along Lake Park Drive is the removal of the manlift (exterior elevator) on the south side of the project. 'We also work from the top down for cleanliness and further efficiency.' 'We always have a trade chasing another trade for instance, the painters will follow the drywall installers,' explained superintendent Zach Garcia. It also will allow for areas that are already primed and painted to undergo the pre-punch and final painting under permanent lighting.Īpproximately 400 trades people are moving through the phases – some simultaneously and some in succession. 'We need electrical in place before we can test the air handler units, fire alarm systems and make sure all building systems operate as intended.' Driver, general contractors for the project. 'This allows us to start testing and continue our systems commissioning process,' said Tom Groenendal, Senior Superintendent for C.W.

broken image

This marks yet another milestone reached as development continues to move forward with finishes on the exterior and the interior. Southern California Edison recently completed the task of providing permanent power to the Soboba Replacement Casino and Resort Project in San Jacinto.

broken image